Cash Flow Tip 12 - Rapid Close-Out = Good Cash Flow

If you effectively manage the startup and the close-out of the project, then the execution in-between mostly takes care of itself.

D. Brown Management Profile Picture
Share

Effective project startup includes getting the contractual details, planning, and the Schedule-of-Values right.  

Cash Flow: Tip 12 Effective Close-Out - Getting Off the Job and Paid

There is a standing joke about the last 10% of a construction project costing 20%. It only causes so much uncomfortable laughter because it happens so often. Effective close-out includes:

  • Start with a detailed log of ALL deliverables required at the submittal stage before installation starts and the close-out stage, including warranties, testing certs, etc. 
  • Keep your change orders tightly managed throughout the project, reviewing progress weekly and escalating problems where appropriate.
  • Do your own punch list walk of the project each week to identify little details that can be buttoned up BEFORE the inspector, engineer, architect, or your customer catches them. Integrate these into the "C-Level" tasks in your ABC Daily Planning
  • Start working on your close-out deliverables as soon as you can. Manage those items as rigorously as you manage your submittals during startup.  
  • Start having weekly demobilization planning meetings when you are within 6 weeks of completion to review every aspect of getting off the job efficiently.  

More from D. Brown Management
Learning, Doing and Teaching
Growth in life, career, and business is about a continual cycle of learning, doing, and teaching.
Executive Briefing - Understanding Industry Trends
The construction industry is changing at an unprecedented rate. The challenges for contractors are compounded by the shortage of talent at all levels, including craft, management, and technical experts.
Be Specific About Problems
The business of construction is filled with constant problems. It’s not that great contractors don’t have problems, it's that great contractors have learned how to troubleshoot first, which allows them to learn from their problems faster.