Production Tracking - The Basics

The heart of any production measurement is simply “Earned Budget vs. Actual Cost”.

D. Brown Management Profile Picture
Share
Field Productivity: Basic concept of production tracking. From budget to tracking of earned budget vs actual costs. Track Daily and Job-to-Date Progress.
  • Imagine a trench that is 1,000 feet long (task)on a project with a $10,000 budget.  
  • When it is 400 feet complete, it is 40% done. Therefore, the “Earned Budget” is $4,000.  
  • Looking at the daily costs in the field so far, if you have spent $3,500 you are ahead on your production at this stage.  
  • If you had spent $4,500, you would be behind on your production. 

Your actual costs don’t have to be perfect while you wait for them to get to the accounting system and back to you. This is about general directionality and it is better to have immediate feedback so you can take corrective action rather than wait for days or a week plus for more exact information.

Schedule + Production are two foundational key results the Foreman will achieve through their planning. This is all supported by the rest of the project team’s objectives and planning process

Schedule control is about doing what you say when you say you will do it. 

Production control is about minimizing the cost of delivering each task by minimizing every step that does not directly add value.

A Foreman can use production tracking as part of their ABC Daily Planning and continuous improvement.   


Improving Labor Productivity Workshop



Related Training
More from D. Brown Management
Learning, Doing and Teaching
Growth in life, career, and business is about a continual cycle of learning, doing, and teaching.
Executive Briefing - Understanding Industry Trends
The construction industry is changing at an unprecedented rate. The challenges for contractors are compounded by the shortage of talent at all levels, including craft, management, and technical experts.
Be Specific About Problems
The business of construction is filled with constant problems. It’s not that great contractors don’t have problems, it's that great contractors have learned how to troubleshoot first, which allows them to learn from their problems faster.