Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process

A basic Schedule-of-Values (SOV) with flat billings and normal collection processes will yield about a 30% return on capital over the first 12 months of a project when looking at it from a cash basis.

D. Brown Management Profile Picture
Share

This is in the average-high range for contractors, depending on type.  

Cash Flow: Tip 14 Aggressive Billings - Pre-Wiring for Success. From a 12-month 31% return-on-capital at risk which is the high-average for contractors up to a 49% or greater return. Punch-as-You-Go Ensuring Maximum Monthly Billings Percentage of Completions “Sold” Ahead of Billing Change Order Approvals Contractually Required Support Documents Verified Early

Our focus is helping contractors achieve performance in the upper end of their peers, including cash flow. Look at the differences that aggressive management of every aspect of billings can make:

 


Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Related Training
Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Change Tracking Log & Management
Great change management starts with a good tracking system. The far more important part of change management is the rigorous review process at least 2X monthly with your PMs that will limit your risk, increase your opportunities, and train your team.
Succession Fact #3: Trust Between Parties
Succession Fact #3: No exit strategy or deal structure will work without trust between all major stakeholder groups. Whether it is a large and complex project or a business ownership transition, there will never be a “perfect” set of documents or plan.
6 Phases of the Strategy and Planning Process
The strategy and planning process for a contractor can be broken down into six phases. Each phase is integrated but has a different objective and involves different people. These phases will help you create the right process for your stage of growth.