Time-on-Tools and Minimum Required Installation

Labor productivity IS NOT the biggest problem with project productivity.

D. Brown Management Profile Picture
Share
Field Productivity: Labor Productivity IS NOT The Biggest Problem With Project Productivity

Under similar conditions the variation in how fast two crafts people actually “turn wrenches” is not that big.  For a specialty contractor nearly every process in the company must be focused around these three areas:

  1. Maximize Time-on-Tools (ToT):  Ensure that crafts people spend most of their day working with their tools actually installing things.  Different studies place the industry average between 50-65%.  Leverage the 6 Pillars of Productivity and ABC Daily Planning.  
  2. Minimum Required Installation:  Don’t take critical shortcuts but don’t over-build the project.  In the field we would call it “Gold Plating.” Effective installation details, craft training and good field supervision practices will ensure that you get the right level of quality. 
  3. Minimize Rework:  The only greater waste than installing more than what is required is doing it twice.

General Contractors and Project Owners can do a lot to set the conditions for success with their labor-intensive subcontractors. 


4 Elements of an Effective Task

Site Logistics Management

What is Lean Construction? 

Improving Labor Productivity Workshop




The Stress-Performance Curve (Yerkes-Dodson Law)
Achieving maximum performance from yourself and your team requires understanding the stress-performance curve as it relates both to individuals and types of work.
Definition of Sustainability
How sustainable is your construction business? Not your ability to build sustainable buildings, but the true sustainability of your business.
Two Key Results for Project Planning
There are two critical key results that should be focused on as part of every project planning process.