Pull Planning - 4 Most Powerful Words

“What do you need?” are the four most powerful words for driving productivity in the construction industry.

D. Brown Management Profile Picture
Share

I learned this lesson from two superintendents from two different general contractors who were building identical projects in different parts of town in 1990.  

Lean Construction Tools: The Four Most Powerful Words for Improving Productivity, What Do You Need?

One superintendent was very experienced and directed all of the subcontractors on what to do.  The other superintendent had almost no experience and would get all the subcontractors together in his trailer looking at the project schedule together on the wall.  He would then pull out his notepad and start asking each of us “What do you need?” He wrote it all down and worked hard to get us what we needed so we could do our work effectively.  

The project with the less experienced superintendent finished 3 months earlier with less change orders!

In 1990 the term lean was only starting to get used in the world as a whole based on a paper written by John Krafcik in 1988.  It wasn’t until 1997 that the Lean Construction Institute was founded and their flagship tool called the Last Planner System was introduced.  

Lean tools and the Last Planner System really just codify what the best superintendents and managers have been doing creating a scalable system. 

Pull Planning is a lean construction practice.




Production Tracking - Don't Be a Dry Monkey
Put a few monkeys in a cage with a ladder that has bananas on top. One monkey immediately goes for the bananas. Cold water sprays on the others. Don't let anyone on your team be a dry monkey when it comes to production tracking or schedule management.
Issue 9 of 9: Low Barriers to Entry
Construction Ownership Transition Issue 9 of 9: There are Few Barriers to Entry for New Contractors. About 500 construction contractors start up each day. In most cases, a new contractor starting up will cause a serious talent drain and add competition.
Site Logistics Manager
About 20% of the field labor hours are spent on material logistics and daily mobilization, demobilization to the work area. What if you could shift 5% of the time spent on logistics to installation while accelerating your foreman development?