Pull Planning - 4 Most Powerful Words

“What do you need?” are the four most powerful words for driving productivity in the construction industry.

D. Brown Management Profile Picture
Share

I learned this lesson from two superintendents from two different general contractors who were building identical projects in different parts of town in 1990.  

Lean Construction Tools: The Four Most Powerful Words for Improving Productivity, What Do You Need?

One superintendent was very experienced and directed all of the subcontractors on what to do.  The other superintendent had almost no experience and would get all the subcontractors together in his trailer looking at the project schedule together on the wall.  He would then pull out his notepad and start asking each of us “What do you need?” He wrote it all down and worked hard to get us what we needed so we could do our work effectively.  

The project with the less experienced superintendent finished 3 months earlier with less change orders!

In 1990 the term lean was only starting to get used in the world as a whole based on a paper written by John Krafcik in 1988.  It wasn’t until 1997 that the Lean Construction Institute was founded and their flagship tool called the Last Planner System was introduced.  

Lean tools and the Last Planner System really just codify what the best superintendents and managers have been doing creating a scalable system. 

Pull Planning is a lean construction practice.




Accelerating The Pace of Learning
Closing the gap between where we are and where we want to be starts with learning new things and accelerating the pace of our learning.
End of Easy
Don’t give up just when the going gets tough, that should be your starting point. Know that most others have given up at this same point, so success and competitive advantage is probably just around the corner from when things begin to get tough.
Weekly Design Meetings and Protecting Finishes
Finishes and other key design elements are important for both the project owner and architect. A contractor providing preconstruction services must focus on protecting these throughout the design-development process.