Project Delivery - CM Agency or Multi-Prime

Project Owners can minimize the markups for overhead and profit (OH&P) by contracting directly with the specialty contractors and hiring a Construction Management (CM) firm to work as their agent.

D. Brown Management Profile Picture
Share

This project delivery method is called CM Agency or CM Multi-Prime.

CM at Risk: Project Delivery Methods - Definition of CM Agency and pros and cons.

The role of the CM is expected to be the same as the CM at Risk method but without direct ties to the contractors. This eliminates conflicts of interest for the CM with the intention of allowing the CM to act 100% for the benefit of the project owner.  

While the OH&P savings can be substantial and the conflict of interest concern for the CM role is minimized, there are downsides that must be weighed to ensure this delivery method is best for the project.  

  • The CM does not have the financial or other risks of construction, which are all passed directly to the Project Owner. This makes the selection process for the right CM firm very critical.
      
  • Between no early involvement of key specialty contractors and the CM not having the financial risk of financial overruns against a Guaranteed Maximum Price (GMP) can lead to change orders and schedule delays similar to the Design-Bid-Build method

Project Delivery - CM Agency or Multi-Prime
The preferred project delivery method. There is a reason 100 of ENR's Top 400 General Contractors use CMAR as the project delivery method for over 75% of their work. Leverage CMAR as part of your growth strategy....

Project Delivery - CM Agency or Multi-Prime
The preferred project delivery method. There is a reason 100 of ENR's Top 400 General Contractors use CMAR as the project delivery method for over 75% of their work. Leverage CMAR as part of your growth strategy....

Situational Awareness - Learning to See
It is critical for project teams to develop a model of the project in their minds so that they can quickly make the thousands of decisions required to keep the project on-track. This is called Situational Awareness and includes three basic layers.
Cash Flow Tip 18 - Making Cash Flow a Game
Imagine creating a culture where everyone ran into work with the same energy that fans and players run into a sporting event.
Budgeting the Right Time for New Tools
Have you ever created a tool or process for your company only to find that people aren’t using it effectively and some don’t even know about it?