Production Tracking - The Basics

The heart of any production measurement is simply “Earned Budget vs. Actual Cost”.

D. Brown Management Profile Picture
Share
Field Productivity: Basic concept of production tracking. From budget to tracking of earned budget vs actual costs. Track Daily and Job-to-Date Progress.
  • Imagine a trench that is 1,000 feet long (task)on a project with a $10,000 budget.  
  • When it is 400 feet complete, it is 40% done. Therefore, the “Earned Budget” is $4,000.  
  • Looking at the daily costs in the field so far, if you have spent $3,500 you are ahead on your production at this stage.  
  • If you had spent $4,500, you would be behind on your production. 

Your actual costs don’t have to be perfect while you wait for them to get to the accounting system and back to you. This is about general directionality and it is better to have immediate feedback so you can take corrective action rather than wait for days or a week plus for more exact information.

Schedule + Production are two foundational key results the Foreman will achieve through their planning. This is all supported by the rest of the project team’s objectives and planning process

Schedule control is about doing what you say when you say you will do it. 

Production control is about minimizing the cost of delivering each task by minimizing every step that does not directly add value.

A Foreman can use production tracking as part of their ABC Daily Planning and continuous improvement.   


Improving Labor Productivity Workshop


Production Tracking - The Basics
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Production Tracking - The Basics
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Impacted Productivity - Disrupted Workflow (No Schedule "Flow")
One of the biggest impacts to productivity in construction is when tasks cannot be completed as planned. When this happens frequently, it starts to impact every aspect of the contractor’s scoreboard in a negative way starting with customer satisfaction.
Four Critical Elements of an Effective Task
Maximizing labor productivity starts with defining exactly what needs to be delivered and then breaking it down into tasks that can be effectively managed.
Problem-Resolution Cost Pyramid - Earlier is Always Better
An easy way to visualize the cost of problem resolution at different stages of construction is with this pyramid. The cost of the problem is the cost of the problem (1X). Finding it ahead of time minimizes the costs and maximizes customer satisfaction.