Problem-Resolution Cost Pyramid - Earlier is Always Better

An easy way to visualize the cost of problem resolution at different stages of construction is with this pyramid.

D. Brown Management Profile Picture
Share

To illustrate this, we will use a common example of a commercial kitchen equipment plan not being fully coordinated with the electrical plans.  

Field Productivity: Problem-Resolution Cost Pyramid. Example of the electrical power plan not matching the kitchen equipment drawings. Before starting work the impact would be 1X, During and requiring rework, 3X. After completion causing delays and major rework the problem could easily cost 10X. Learn to identify problems early and mitigate.

A piece of equipment requiring a dedicated circuit is shown on the panel schedule but not the power plan so it was easy to miss in the estimate. When the problem is identified determines the total cost of fixing the problem:

  • Before - some plastic conduit run under slab, some wire, and a couple hours (max) of time.  
  • During - more expensive metal conduit run overhead and 6-8 hours of time.
  • After - remobilization time to the work area, protection for finishes, working above hard lid ceiling, etc. plus the customer is likely frustrated.  

The cost of the problem is the cost of the problem (1X). Finding it ahead of time minimizes the costs and maximizes customer satisfaction. Finding it during construction will cost about 3X and after construction 10X+.  


What systems do you have in place to find problems early? Create a checklist by phase of work that helps identify potential problems early.

How many problems did you have last month that could have been found earlier? Study all your RFIs and Change Orders for the last month. Could they have been identified sooner? Put those items on your checklists (above). Repeat each month with your top PM, Estimator, and Field Leader. You will be surprised at how quickly you improve profitability and customer satisfaction while lowering stress. Contact us to schedule time to talk about how we have approached this in the past. We will freely share all lessons-learned, both the good and the bad. 

Early identification is a trainable skill and a workflow process including checklists

 


Problem-Resolution Cost Pyramid - Earlier is Always Better
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Problem-Resolution Cost Pyramid - Earlier is Always Better
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Impacted Productivity - Fighting Back
Fighting back effectively against labor productivity impacts will significantly improve project outcomes including customer satisfaction if handled properly. There are four interrelated aspects to effectively fighting back.
Early Identification is a Process - Effectively Using Checklists
Few things will improve customer satisfaction, profitability, cash flow, risk, and team stress more than early identification of change orders. This is a process and a trainable skill. Checklists are some of the most valuable tools in that process.
Change Order Profit Improvement
A 10% improvement in change order pricing for a $50M per year contractor will add $500K to their bottom line. This is not about simply marking up the change more, but rather, including the many costs that are typically missed or undervalued.