Percent Planned Complete (PPC) - Calculation Example

Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.”

D. Brown Management Profile Picture
Share
Field Productivity: Percent Planned Complete (PPC). Do or do not. There is no try.

This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement. Measurement of PPC is rigorous:

  • Partially complete tasks DO NOT count.
  • Extra tasks (not planned) DO NOT count.
  • Reasons why DO NOT matter except for the weekly learning aspect. 

Imagine designing a field supervisor coaching program with PPC at the center.  

For 12 weeks, an experienced coach would work hands-on with a Foreman starting with a review of their PPC from the prior week and then developing the next week’s Short-Interval-Plan (SIP), focusing on:  

This coaching will improve the Foreman’s capability to execute their key responsibilities and achieve their key results.  


Field Productivity Workshop


Percent Planned Complete (PPC) - Calculation Example
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Percent Planned Complete (PPC) - Calculation Example
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Changes - Impacts Beyond the Direct Costs
Contractors don't typically see the full negative impact of changes and, therefore, don’t put the right level of resources into their management.
Lean Principle - 3 Enemies of Lean
Profitable growth comes from operating within a target capacity and capability range - and continually increasing those ranges. Operating with consistent overload, consistent under capacity, or with consistently high variability is not sustainable.
Lean Principle - Observation (Gemba Walks and Learning to See)
One of the most important tools for improving productivity is going to the jobsite or work area and observing for an extended period of time with the intent to understand but not to immediately interact. Observation progresses through about 7 stages.