Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)

The biggest risk for a specialty contractor is the performance of on-site labor.

D. Brown Management Profile Picture
Share

One of the biggest impacts to labor productivity is having a schedule that requires large variations in labor. The most ideal situation is to have a steady ramp up, stable crew size during peak production followed by a steady demobilization.

Field Productivity: Impacts - Unleveled Manpower Schedule.

 

No project will be perfect and impacts to highly variable labor requirements include:

  • Overloading the project to meet demands resulting in too many people during downtimes, which then lowers productivity.  
  • Learning curve for new team members coming on and off the project. Studies show that productivity can be impacted by as much as 10% during the first week for a craftsperson learning a new project. 
  • Overtime required to meet the schedule. Not only will you have the increased cost per hour, but you will experience a decrease in productivity and safety. Four weeks at 5-10’s will impact productivity by 20%.
  • Poor scheduling often goes hand-in-hand with stacking of trades which can cost another 10-50% decrease in productivity for those areas.  
  • There is an increase in the coordination time it takes to move manpower on and off the project which has a direct cost as well as an indirect cost from dilution of management.  

 

 

 


Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Impacted Productivity - Stacking of Trades and Installation Efficiency
Each craftsperson needs about 200 usable square feet for a productive installation. This assumption is included in production units used to estimate and budget projects. Having less than that can impact productivity up to 50%.
Early Identification is a Process - Effectively Using Checklists
Few things will improve customer satisfaction, profitability, cash flow, risk, and team stress more than early identification of change orders. This is a process and a trainable skill. Checklists are some of the most valuable tools in that process.
The Average Field Day in Detail (Craft Labor + Foreman)
Labor is often the biggest cost variable on a construction project. Just over half the field hours are related to actual installation. Understanding how time is spent on average in the field is the first step to improving field productivity.