Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)

The biggest risk for a specialty contractor is the performance of on-site labor.

D. Brown Management Profile Picture
Share

One of the biggest impacts to labor productivity is having a schedule that requires large variations in labor. The most ideal situation is to have a steady ramp up, stable crew size during peak production followed by a steady demobilization.

Field Productivity: Impacts - Unleveled Manpower Schedule.

 

No project will be perfect and impacts to highly variable labor requirements include:

  • Overloading the project to meet demands resulting in too many people during downtimes, which then lowers productivity.  
  • Learning curve for new team members coming on and off the project. Studies show that productivity can be impacted by as much as 10% during the first week for a craftsperson learning a new project. 
  • Overtime required to meet the schedule. Not only will you have the increased cost per hour, but you will experience a decrease in productivity and safety. Four weeks at 5-10’s will impact productivity by 20%.
  • Poor scheduling often goes hand-in-hand with stacking of trades which can cost another 10-50% decrease in productivity for those areas.  
  • There is an increase in the coordination time it takes to move manpower on and off the project which has a direct cost as well as an indirect cost from dilution of management.  

 

 

 


Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Understanding the Construction Field Day
For a contractor to truly improve their field productivity, they must start with understanding how the time is spent. Depending on the trade, project, and the labor, study the time spent on actual installation ranges from 50-64%.
Percent Planned Complete (PPC) - Calculation Example
Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.” This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement.
Early Identification is a Process - Effectively Using Checklists
Few things will improve customer satisfaction, profitability, cash flow, risk, and team stress more than early identification of change orders. This is a process and a trainable skill. Checklists are some of the most valuable tools in that process.