Higher Scores Aren’t Always Better: Percent Planned Complete (PPC) Example

Construction is full of competitive personalities - more is always better. This is not always the case, and you must be careful when setting targets that your goals don't have unintended consequences. Percent Planned Complete (PPC) is a perfect example.

Joseph Irby Profile Picture
Share

 

 

Percent Planned Complete (PPC) is a critical measure of a weekly work plan or SIP (Short-Interval Plan). 

David MacNeel from On Point Lean describes that higher scores aren't always better in this interview with Felipe Engineer-Manriquez on the EBFC (Easier, Better, for Construction) Show (4 minutes starting at 0:20:00)

 

 

54% was the average amount of weekly tasks that got completed as planned when Greg Howell and Glenn Ballard first studied the problem in the late 90s. 

Low to Mid 70s: Likely on-track with schedule and productivity (Two Key Results for Project Planning)

High 70s to High 80s: Likely ahead of schedule and productivity targets. 

High 80s to Low 90s: Great team and conditions.

Mid to High 90s: Likely gaming the system - sandbagging or misreporting. 


 

An important part of your scorekeeping process is setting appropriate targets with tolerances and clear management escalations if there are large variances, or they are trending in the wrong direction for too long. 

 



Related Training

Continuous Improvement: Plan, Do, Check, and Act (PDCA)
Improving productivity in construction is exceptionally challenging. It must be embraced as a journey and not a destination. It must be made into a game so that people clearly see what winning looks like and fall in love with the process.
Lean Principle - Kaizen (Every Detail Matters)
As contractors build their businesses, it is important to look at every detail from the first meeting with a potential customer through winning and building the project. This same attention to detail also applies to supporting operations and talent.
Last Planner System (LPS) Overview: Should > Can > Will > Did > Improve
The Last Planner System (LPS) developed by the Lean Construction Institute (LCI) is the codification of the practices used by the best project teams. There are elements that EVERY contractor can use to improve performance of their projects and business.