Agile Project Management vs. Critical Path Method

The Critical Path Method (CPM) of project management is very commonly used in the management of construction projects.

D. Brown Management Profile Picture
Share

CPM works very well when the components of the design and the project are mostly known to all responsible parties. CPM focuses on either a single value-delivery event such as the completion of a building or in major phases such as turning over a floor at a time.  

Management Tools: Agile Project Management vs Critical Path Method (CPM).

CPM does not work as well in situations where there are significant “Known-Unknowns” about the plan CPM really breaks down when there are “Unknown-Unknowns”:

  • The final destination isn’t crystal clear; even to the leader
  • The path to get there has unknowns
  • The tools and tactics required to get there aren’t known to the team

In these situations more agile management methods are required either in conjunction with or to replace CPM:

There are similarities between all methods.  Develop the systems that work best for your company at this point in time.




Improving Team Morale
If morale on your team is low then it’s probably your fault. Those words sound harsh but let’s unpack them a little bit and see if we can improve team morale.
Issue 1 of 9: Strength of the Management Team
Construction Ownership Transition Issue 1 of 9: Strength and Alignment of the Management Team. Beyond liquidation, nearly 100% of the value of a construction business is based on the management team's ability to profitably grow the business.
Helen Keller - Blind vs Vision
As a contracting business grows it becomes more important the team is aligned around a common vision and culture. It becomes even more critical if the company has more than one geographic location.